Saudi Arabia's first wind project reaches financial close

22/07/2019 Argaam

 

The consortium comprising EDF Renewables and Abu Dhabi Future Energy Company (Masdar) has completed the financing for the $500-million Dumat Al Jandal wind project in Saudi Arabia, it said in statement on Monday.

 

The funding has been secured from Saudi and international banks, it said, without disclosing bank names.

 

Project construction will begin shortly with commercial operations expected to start in the first quarter of 2022.

 

Vestas will be responsible for the engineering, procurement and construction (EPC) contract. TSK will be responsible for the balance of plant, while CG Holdings will provide the substations and high-voltage solutions.

 

In January, the consortium was awarded contract by the Saudi Ministry of Energy, Industry and Mineral Resources following the submission of a bid of 21.3 per megawatt hour (MWh) for the project.

Comments {{getCommentCount()}}

Be the first to comment

{{Comments.indexOf(comment)+1}}
{{comment.FollowersCount}}
{{comment.CommenterComments}}
loader Train
Sorry: the validity period has ended to comment on this news
Opinions expressed in the comments section do not reflect the views of Argaam. Abusive comments of any kind will be removed. Political or religious commentary will not be tolerated.

Most Read