Najran Cement Company announced commencement of the commercial operation of its third clinker line as of 21/9/2013 with a design capacity of 6500 tonnes/day after successful tests of the line’s full capacity and actual capacity of 7000 tonnes/day for seven consecutive days.
The production during the test phase reached 375,180 tonnes with a financial effect of around SAR 45 million.
Be the first to comment
Comments Analysis: