18/09/2012 Argaam

Further to the company's announcement on 29/4/2012 regarding the delay of the operation of the third mill in Jazan plant, the company announces the delay of the project for further (4) months for reasons beyond its control, as the manufacturing company (Christian Pfeiffer) has delayed the approval of the civil drawings and the shipment of the mill equipment.

It is expected that the third mill operation will be on 29/1/2013, God will.