Infrastructure of Jazan residential project is 65 % complete:

25/12/2013 Argaam

Jazan Development Company announced today on tadawul the latest updates regarding its residential project occupying  146,000 m2 in Jazan as follows:

  • The progress in implementing the project’s infrastructure has reached 65% with expected completion date on 30/5/2014.
  • The infrastructure is being implemented within budget without any significant overrides.
  • The project’s delay due to contractors’ insolvency and licensing delay is not likely to affect the company’s financial results negatively.