Saudi Ceramics plant expansion delayed till Nov 30

29/06/2015 Argaam

Saudi Ceramics Company plans to complete the expansion of its second water heaters plant by November 30, instead of the previously scheduled date set by mid-2015, the company said on Monday in a statement to Tadawul.

The plant, which is 85 percent completed, was delayed due to a change in the factory’s technical specifications.

Costs of the delay in operating the plant are limited and wont affect the companys results, it added.

In February 2013, Saudi Ceramics approved a SAR 76 million plan to expand its second water heaters plant in the industrial city in Riyadh. After the expansion, the plant is expected to produce an additional 600, 000 water heaters a year, according to Argaam data. 

Second Water Heaters Plant Expansion


News

Prices

Aramco IPONew

Sectors

Companies

Financial Data

Financial Ratios

Analysts

IPOs

Economy

Mutual Funds

Projects

Interactive Charts