| Previous Announcement | Al-Jawhara Al-Kobra Project (The Village) |
| Date of Previous Announcement on Tadawul's Website | 2022-09-19 Corresponding to 1444-02-23 |
| Percentage of fulfilled achievement | Total achievement 99%, representing: 100% of structure works and concrete works, 100% of electromechanical works, 100% of facade works, and 99% of interior finishing works |
| Event's Expected Completion Date | As per the latest report received from the developer partner, construction of the project completed and accordingly, the project will be operational in the second quarter 2023G |
| Reasons for Exceeding the Announced End Date | Awaiting final approvals for the actual operation of the mall |
| The costs associated with the event, and if they have changed or not with indication of the reasons. | There is no change from the previously announced cost |
| Impact of the Delay on the Company's Financial Results | No impact. |